Verdi CMAR Riverbed Restoration Design

The Nevada Department of Transportation has classified two bridges along Interstate 80 as scour critical, and has contracted Granite Construction on a Construction Manager at Risk (CMAR) basis to design and implement a scour protection plan. Balance worked in concert with Wood Rodgers to fulfill environmental permitting requirements for the project, including development of [...]

Verdi CMAR Riverbed Restoration Design2018-01-16T23:47:51+00:00

San Felipe Creek Restoration

The Santa Clara Valley Habitat Agency (Habitat Agency) represents multiple stakeholders in providing long-term protection of ecosystems and biodiversity within Santa Clara County. The Habitat Agency contracted with Habitat Restoration Sciences (HRS), Balance Hydrologics, Inc., and Dudek for this design-build project to develop conceptual plans, evaluate the feasibility of restoration opportunities, and implement the [...]

San Felipe Creek Restoration2020-11-02T18:27:22+00:00